Deals
The AI buildout is a lease book as much as a model race: megawatts, GPU queues, server backlogs, and the landlords who sit between the lab and the substation. This page tracks those deals as they appear in Aigentic Daily — with nulls for unknowns, not guesses.
Filter by text, status, who, or counterparty. Sort by announced date (newest first by default), who, or capacity. A backlog is labeled as a backlog; a lease is labeled as a lease. Source links go to the Daily edition or the outlet that carried the print.
Not investment advice. Sourced from public reports; figures can lag or get revised.
Status
Showing 28 of 28 deals
Dell Technologies
Sep 2, 2026
Announced · AI server capacity reservation / backlog
$95B AI backlog; $60.9B AI server orders in fiscal Q2
- Counterparty
- AI server customers (6,500+ AI customers cited)
- Where
- Global (Round Rock, Texas HQ)
- Amount
- $95B
- MW
- —
- GPUs
- —
Earnings print, not a single bilateral lease: record $60.9B AI server orders in quarter ended July 31; $16.4B AI-optimized server revenue; exited with $95B AI backlog. Labeled as capacity reservation / server backlog, not MW or site power.
Anthropic
Sep 1, 2026
Announced · Data center / power lease
~350 MW Texas campus; $35B cloud-computing commitment
- Counterparty
- Lambda (Nvidia-backed); Hut 8 developing campus; Nvidia reportedly holds lease
- Where
- Nueces County, Texas, US
- Amount
- $35B
- MW
- 350
- GPUs
- —
Reuters (source) and WSJ first report: Anthropic signed a $35B cloud deal with Lambda for a Hut 8 Texas DC at about 350 MW; WSJ said Nvidia would hold the lease. Parties did not immediately comment.
Emerald AI
Aug 28, 2026
Under construction · Power-flexible AI factory / data center
Nearly 100 MW Vera Rubin power-flexible AI factory
- Counterparty
- Digital Realty; Nvidia; tested with EPRI, Dominion, PJM
- Where
- Manassas, Virginia, US
- Amount
- —
- MW
- 100
- GPUs
- —
Company announcement via VentureBeat (Aug 25 round context; Closing Time Aug 28): Manassas project with Digital Realty and Nvidia, nearly 100 MW, slated later this year. Equity round ($150M Series A) is separate; this row is the site/power project.
Microsoft
Aug 28, 2026
Announced · GPU lease (neocloud financing)
~$1B short-dated private debt to buy Nvidia GPUs Microsoft will lease
- Counterparty
- Lambda (Nvidia-backed); JPMorgan-arranged debt
- Where
- Undisclosed
- Amount
- $1B
- MW
- —
- GPUs
- —
Bloomberg / TechCrunch: Lambda raised about $1B short-dated private debt arranged by JPMorgan to buy Nvidia GPUs that Microsoft will lease; separate ~$926M term loan that week. GPU count not printed.
Amazon Web Services
Aug 27, 2026
Announced · GPU capacity expansion
2 million Nvidia GPUs across 2027–2028 (on top of 1M agreed March)
- Counterparty
- Nvidia
- Where
- AWS regions (undisclosed)
- Amount
- —
- MW
- —
- GPUs
- 2,000,000
TechCrunch on Nvidia earnings call: AWS will add two million Nvidia GPUs across 2027 and 2028, atop one million agreed in March. Terms undisclosed.
Anthropic
Aug 26, 2026
Announced · AI cloud compute rental
~460 MW; Nvidia Vera Rubin; ~6-year commitment; start ~end-2027
- Counterparty
- Nscale (UK neocloud)
- Where
- West Virginia, US
- Amount
- $45B
- MW
- 460
- GPUs
- —
Bloomberg first, CNBC confirmed: ~$45B to rent capacity at Nscale’s flagship West Virginia development; ~460 MW; Vera Rubin hardware; people said six years and end-of-2027 start.
AM Intelligence
Aug 26, 2026
Announced · GPU systems order / gigawatt compute plan
9,000 Nvidia Vera Rubin systems; $8B plan for ~1 GW compute
- Counterparty
- Nvidia (systems order); Greenko-backed
- Where
- Southern India
- Amount
- $8B
- MW
- —
- GPUs
- 9,000
Bloomberg: Greenko-backed AM Intelligence placed a binding order for 9,000 Vera Rubin systems under an $8B plan to stand up a gigawatt of compute; servers slated next year in southern India.
Nvidia
Aug 24, 2026
Announced · Power / site investment (Stargate campus)
Stargate campus power landlord stake; dollar size only described as billions
- Counterparty
- Lancium (Stargate power developer); OpenAI explored stake then walked
- Where
- Abilene, Texas, US
- Amount
- —
- MW
- —
- GPUs
- —
The Information: OpenAI explored investing in or acquiring Lancium (power developer behind Stargate in Abilene) last quarter before Nvidia put billions into the same firm. Exact check size beyond 'billions' not printed.
Nvidia
Aug 22, 2026
Announced · Power-and-site developer partnership / minority stake
Site, power, cooling, compute decisions via Nvidia DSX; stake size undisclosed
- Counterparty
- Cloverleaf Infrastructure
- Where
- US (utilities ↔ data-center developers)
- Amount
- —
- MW
- —
- GPUs
- —
TechCrunch: Nvidia partners with Cloverleaf (2024 power-and-site developer that raised $300M that year) and takes a minority stake; size undisclosed (other reports: hundreds of millions). Extends Nvidia’s infrastructure bets after $1.5B SB Energy stake tied to OpenAI’s Ohio campus.
Amazon Web Services
Aug 18, 2026
Under construction · Multi-campus data center investment / lease campuses
Three campuses; planned investment raised to $18B (from $12B in Feb); MW not disclosed in Amazon release
- Counterparty
- STACK Infrastructure (developer/owner cited in coverage); SWEPCO (power)
- Where
- Caddo & Bossier Parishes / Shreveport, Louisiana, US
- Amount
- $18B
- MW
- —
- GPUs
- —
Amazon Aug 18, 2026 update of Feb $12B plan: third Shreveport campus brings NW Louisiana planned investment to $18B. No IT-load MW in Amazon’s own release.
OpenAI
Aug 17, 2026
Under construction · Data center lease / AI factory campus (PORTS-Pike)
~8 GW-IT under 20-year lease; initial 4.25 IT-GW with Nvidia credit support; first ~800 MW targeted 2028
- Counterparty
- SB Energy (SoftBank-controlled); Nvidia (exclusive compute + credit support)
- Where
- Pike County, Ohio, US (PORTS-Pike / former Portsmouth site)
- Amount
- —
- MW
- —
- GPUs
- —
OpenAI Aug 17, 2026: ~8 GW-IT at PORTS-Pike; SB Energy builds/owns/operates under 20-year lease; Nvidia exclusive AI compute, $1.5B SB Energy investment, credit support on initial 4.25 IT-GW (SEC residual-value guarantee capped at $105B cited elsewhere — not campus lease rent). First 800 MW expected 2028. Later Daily/CNBC covered SB Energy S-1 dependency on OpenAI as tenant.
CoreWeave
Aug 4, 2026
Announced · Data center expansion / contracted IT power
360 MW contracted IT power across three facilities; expected online 2028
- Counterparty
- Indonesia facilities (own-and-operate; three sites)
- Where
- Indonesia (Asia-Pacific; first CoreWeave APAC DCs)
- Amount
- —
- MW
- 360
- GPUs
- —
Reuters / CoreWeave Aug 4, 2026: three Indonesia facilities totaling 360 MW contracted IT power, own-and-operate, targeted 2028. Capex not disclosed in the Reuters brief.
Brookfield (developer/operator selected by DOE)
Jul 29, 2026
Announced · AI/HPC campus on former enrichment site + dedicated power
Up to ~1.8 GW utility / >1.2 GW compute stated; $100B investment figure in coalition release
- Counterparty
- NextEra Energy (dedicated generation); U.S. DOE Paducah Site
- Where
- McCracken County, Kentucky, US (Paducah American Energy Hub)
- Amount
- $100B
- MW
- 1200
- GPUs
- —
Coalition Jul 29, 2026 via Axis: Brookfield+NextEra on DOE Paducah Site. DOE Aug 4 account differs on completion year (2031 vs 2032) and phrasing of capacity. $100B is stated investment, not a signed tenant offtake. PSC approval still required for power service agreement.
Meta Platforms
Jul 28, 2026
Under construction · Data center JV / lease of entire campus
1 GW compute capacity campus; ~$14B development costs; Meta leases entire campus; online beginning ~2028
- Counterparty
- BlackRock-managed funds (80% venture interest); Meta 20%
- Where
- El Paso, Texas, US
- Amount
- $14B
- MW
- —
- GPUs
- —
Meta/BlackRock Jul 28, 2026: 80/20 venture; ~$14B development costs; 1 GW compute; Meta sole initial occupant via lease. RVG aggregate ~$13B cited in Meta release.
OpenAI
Jul 22, 2026
Announced · Self-build AI data center campus + power contract (Project Camellia)
3.2 GW contracted power phased 2028–2032; county framed ~$20B minimum investment
- Counterparty
- Georgia Power (power offtake); self-develop campus
- Where
- Effingham County, Georgia, US (Savannah Gateway Industrial Hub)
- Amount
- $20B
- MW
- —
- GPUs
- —
OpenAI Jul 22, 2026: designing/developing Camellia; 3.2 GW from Georgia Power phased 2028–2032. $20B is the county/incentive framing (Bloomberg cited >$30B at full build — not used as amountUsd). Acres (~1,400) from local coverage of four-building campus. Power figure is contracted utility delivery, not disclosed critical IT load.
Nvidia (reported tenant; Hut 8 named only as investment-grade)
Jul 20, 2026
Under construction · Data center lease (15-year phases; campus commercialization)
704 MW IT across two 352 MW leases; 1 GW utility campus; $19.6B base-term contract value
- Counterparty
- Hut 8 (Beacon Point campus)
- Where
- Nueces County, Texas, US (Beacon Point)
- Amount
- $19.6B
- MW
- 704
- GPUs
- —
Hut 8 Jul 20, 2026: second 15-year $9.8B / 352 MW lease doubles same IG tenant to 704 MW IT; campus base-term $19.6B (renewals could reach ~$50.2B). FT later named Nvidia as tenant; Hut 8 release did not name the counterparty. Related but distinct from Anthropic’s later Lambda cloud offtake on the same campus.
Undisclosed investment-grade global tech tenant
Jul 14, 2026
Announced · Data center lease (20-year NNN)
175 MW critical IT; ~$6.6B contracted revenue initial term (up to ~$11.6B with extensions); deliveries Q4 2027
- Counterparty
- CleanSpark (Sandersville campus)
- Where
- Sandersville, Georgia, US
- Amount
- $6.6B
- MW
- 175
- GPUs
- —
CleanSpark Jul 14, 2026: tenant not named. LOI/exclusivity over CleanSpark Texas portfolio (up to 885 MW) noted but not counted as a separate closed lease.
Meta Platforms
Jul 13, 2026
Under construction · Hyperscaler AI campus expansion (self-build / JV)
Expanded to 5 GW compute capacity; >$50B regional investment; ~2 GW targeted by 2030, full ~2032
- Counterparty
- Blue Owl / Beignet Investors JV; Entergy Louisiana (power)
- Where
- Richland Parish, Louisiana, US (Hyperion)
- Amount
- $50B
- MW
- —
- GPUs
- —
CNBC on Meta Jul 13, 2026: Hyperion raised from prior ~2 GW / $27B JV framing to 5 GW and >$50B. Meta did not separate critical IT load from site power in the announcement; amount is investment figure, not a bilateral lease rent.
Meta Platforms
Jul 8, 2026
Under construction · AI-optimized data center campus (self-build)
1 GW AI-optimized campus; >CAD $13B investment (USD equivalent not converted here)
- Counterparty
- Self-build; Alberta grid partners (Greenlight LP, AltaLink, Capital Power, AESO cited)
- Where
- Sturgeon County, Alberta, Canada
- Amount
- —
- MW
- —
- GPUs
- —
Meta Jul 8, 2026: groundbreaking on 1GW AI-optimized DC in Sturgeon County, Alberta — first Canada site; >CAD $13B investment. amountUsd null (CAD not converted). IT vs gross capacity not separated.
Anthropic
Jul 6, 2026
Announced · Data center lease (20-year)
~401 MW critical IT load; phased H2 2027 → full early 2028; ~$19B contracted lease revenue
- Counterparty
- TeraWulf (Raylan Data LLC)
- Where
- Hawesville / Hancock County, Kentucky, US (Justified Data campus)
- Amount
- $19B
- MW
- 401
- GPUs
- —
TeraWulf Jul 6, 2026 press / 8-K: 20-year lease for ~401 MW critical IT; ~$19B contracted revenue over initial term; IG credit support expected. Separate Abernathy JV sale to Fluidstack-led group is not this row.
Microsoft
Jun 23, 2026
Live · AI data center campus (Fairwater) — first facility live
First Fairwater facility fully operational; MW undisclosed; second facility targeted 2028; Microsoft cites ~$4.7B statewide WI hyperscale construction spend 2024–2028 (not used as deal amount)
- Counterparty
- Self-build (Village of Mount Pleasant / Racine County)
- Where
- Mount Pleasant, Wisconsin, US
- Amount
- —
- MW
- —
- GPUs
- —
Microsoft Jun 23, 2026: first Mount Pleasant Fairwater DC complete/operational after April startup. No IT-load MW in release. Dollar figure in coverage is statewide construction-spend estimate, so amountUsd is null. Acres (315) from campus plan coverage of original site.
Google
Jun 15, 2026
Under construction · Data center campus expansion
$1.5B investment across 2026–2027; site MW undisclosed (300 MW cited as contracted regional generation, not campus IT load)
- Counterparty
- Self-build expansion; TVA region power partners
- Where
- Jackson County, Alabama, US
- Amount
- $1.5B
- MW
- —
- GPUs
- —
Google Jun 15, 2026: $1.5B investment across 2026–2027 to expand Jackson County campus (former Widows Creek coal plant). Critical IT load not disclosed; >300 MW cited as contracted regional generation for TVA area, not campus IT load.
Anthropic
May 3, 2026
Live · Cloud / GPU offtake (Colossus I & II)
~$1.25B/month through May 2029 (~$15B/yr); ~325,000 Nvidia GPUs cited in amended S-1 coverage
- Counterparty
- SpaceX (xAI Colossus campuses)
- Where
- Memphis, Tennessee, US (Colossus / Colossus II)
- Amount
- —
- MW
- —
- GPUs
- 325,000
SpaceX S-1 (May 2026) disclosed Cloud Services Agreements with Anthropic for Colossus/Colossus II at $1.25B/month through May 2029; either party may terminate on 90 days’ notice after ramp. GPU count ~325k from amended S-1 coverage; MW not reliably stated as a single leased figure. amountUsd left null (term depends on duration/termination).
Meta Platforms
Apr 21, 2026
Under construction · AI-optimized data center campus (self-build)
AI-optimized campus; >$1B regional investment; MW not stated in release
- Counterparty
- Self-build
- Where
- Tulsa, Oklahoma, US
- Amount
- $1B
- MW
- —
- GPUs
- —
Meta Apr 21, 2026 (page also shows Apr 20): first Oklahoma AI-optimized DC; >$1B regional investment. Campus MW not disclosed.
Anthropic
Apr 20, 2026
Announced · Cloud compute offtake / capacity envelope
Up to 5 GW new capacity; >$100B AWS tech spend over 10 years; ~1 GW Trainium2+3 targeted by end-2026
- Counterparty
- Amazon Web Services (Trainium / Graviton)
- Where
- AWS regions (incl. Project Rainier / Indiana cited in secondary coverage; sites not fully enumerated in Anthropic release)
- Amount
- $100B
- MW
- —
- GPUs
- —
Anthropic Apr 20, 2026 primary: up to 5 GW and >$100B over ten years on AWS technologies (Trainium2–4, Graviton). Not a named single-site lease; Amazon equity ($5B + up to $20B more) is separate from the offtake spend figure used in amountUsd.
Meta Platforms
Apr 9, 2026
Announced · AI cloud capacity offtake (multi-year)
~$21B expanded agreement through Dec 2032; Vera Rubin deployments; prior relationship brings combined ~$35B cited in coverage
- Counterparty
- CoreWeave
- Where
- Multiple CoreWeave locations (undisclosed)
- Amount
- $21B
- MW
- —
- GPUs
- —
CoreWeave Apr 9, 2026: expanded long-term Meta agreement ~$21B through Dec 2032 for dedicated AI cloud capacity across multiple sites, including early Vera Rubin. MW/GPU counts not in the company release.
Amazon Web Services
Mar 18, 2026
Announced · GPU capacity expansion / reservation
>1 million Nvidia GPUs starting 2026 (Blackwell/Rubin architectures cited)
- Counterparty
- Nvidia
- Where
- AWS regions (global)
- Amount
- —
- MW
- —
- GPUs
- 1,000,000
AWS blog at Nvidia GTC 2026: deploy more than 1M Nvidia GPUs across AWS regions starting 2026. announced date set to mid-March GTC window (exact keynote day not pinned in the blog slug). Aug 2026 +2M expansion tracked separately as aws-nvidia-gpus-2027-2028.
Meta Platforms
Feb 11, 2026
Under construction · AI / hyperscale data center campus (self-build)
Designed for 1 GW capacity; >$10B investment cited
- Counterparty
- Self-build
- Where
- Lebanon, Indiana, US (Boone County)
- Amount
- $10B
- MW
- —
- GPUs
- —
Meta Feb 11, 2026: groundbreaking on 1GW Lebanon, Indiana campus; investment over $10B. IT vs gross capacity not separated.
| Counterparty | What | Where | Amount | Status | Source | |||
|---|---|---|---|---|---|---|---|---|
| Sep 2, 2026 | Dell Technologies | AI server customers (6,500+ AI customers cited) | AI server capacity reservation / backlog | Global (Round Rock, Texas HQ) | $95B AI backlog; $60.9B AI server orders in fiscal Q2 Earnings print, not a single bilateral lease: record $60.9B AI server orders in quarter ended July 31; $16.4B AI-optimized server revenue; exited with $95B AI backlog. Labeled as capacity reservation / server backlog, not MW or site power. | $95B | Announced | Link |
| Sep 1, 2026 | Anthropic | Lambda (Nvidia-backed); Hut 8 developing campus; Nvidia reportedly holds lease | Data center / power lease | Nueces County, Texas, US | ~350 MW Texas campus; $35B cloud-computing commitment Reuters (source) and WSJ first report: Anthropic signed a $35B cloud deal with Lambda for a Hut 8 Texas DC at about 350 MW; WSJ said Nvidia would hold the lease. Parties did not immediately comment. | $35B | Announced | Link |
| Aug 28, 2026 | Emerald AI | Digital Realty; Nvidia; tested with EPRI, Dominion, PJM | Power-flexible AI factory / data center | Manassas, Virginia, US | Nearly 100 MW Vera Rubin power-flexible AI factory Company announcement via VentureBeat (Aug 25 round context; Closing Time Aug 28): Manassas project with Digital Realty and Nvidia, nearly 100 MW, slated later this year. Equity round ($150M Series A) is separate; this row is the site/power project. | — | Under construction | Link |
| Aug 28, 2026 | Microsoft | Lambda (Nvidia-backed); JPMorgan-arranged debt | GPU lease (neocloud financing) | Undisclosed | ~$1B short-dated private debt to buy Nvidia GPUs Microsoft will lease Bloomberg / TechCrunch: Lambda raised about $1B short-dated private debt arranged by JPMorgan to buy Nvidia GPUs that Microsoft will lease; separate ~$926M term loan that week. GPU count not printed. | $1B | Announced | Link |
| Aug 27, 2026 | Amazon Web Services | Nvidia | GPU capacity expansion | AWS regions (undisclosed) | 2 million Nvidia GPUs across 2027–2028 (on top of 1M agreed March) TechCrunch on Nvidia earnings call: AWS will add two million Nvidia GPUs across 2027 and 2028, atop one million agreed in March. Terms undisclosed. | — | Announced | Link |
| Aug 26, 2026 | Anthropic | Nscale (UK neocloud) | AI cloud compute rental | West Virginia, US | ~460 MW; Nvidia Vera Rubin; ~6-year commitment; start ~end-2027 Bloomberg first, CNBC confirmed: ~$45B to rent capacity at Nscale’s flagship West Virginia development; ~460 MW; Vera Rubin hardware; people said six years and end-of-2027 start. | $45B | Announced | Link |
| Aug 26, 2026 | AM Intelligence | Nvidia (systems order); Greenko-backed | GPU systems order / gigawatt compute plan | Southern India | 9,000 Nvidia Vera Rubin systems; $8B plan for ~1 GW compute Bloomberg: Greenko-backed AM Intelligence placed a binding order for 9,000 Vera Rubin systems under an $8B plan to stand up a gigawatt of compute; servers slated next year in southern India. | $8B | Announced | Link |
| Aug 24, 2026 | Nvidia | Lancium (Stargate power developer); OpenAI explored stake then walked | Power / site investment (Stargate campus) | Abilene, Texas, US | Stargate campus power landlord stake; dollar size only described as billions The Information: OpenAI explored investing in or acquiring Lancium (power developer behind Stargate in Abilene) last quarter before Nvidia put billions into the same firm. Exact check size beyond 'billions' not printed. | — | Announced | Link |
| Aug 22, 2026 | Nvidia | Cloverleaf Infrastructure | Power-and-site developer partnership / minority stake | US (utilities ↔ data-center developers) | Site, power, cooling, compute decisions via Nvidia DSX; stake size undisclosed TechCrunch: Nvidia partners with Cloverleaf (2024 power-and-site developer that raised $300M that year) and takes a minority stake; size undisclosed (other reports: hundreds of millions). Extends Nvidia’s infrastructure bets after $1.5B SB Energy stake tied to OpenAI’s Ohio campus. | — | Announced | Link |
| Aug 18, 2026 | Amazon Web Services | STACK Infrastructure (developer/owner cited in coverage); SWEPCO (power) | Multi-campus data center investment / lease campuses | Caddo & Bossier Parishes / Shreveport, Louisiana, US | Three campuses; planned investment raised to $18B (from $12B in Feb); MW not disclosed in Amazon release Amazon Aug 18, 2026 update of Feb $12B plan: third Shreveport campus brings NW Louisiana planned investment to $18B. No IT-load MW in Amazon’s own release. | $18B | Under construction | Link |
| Aug 17, 2026 | OpenAI | SB Energy (SoftBank-controlled); Nvidia (exclusive compute + credit support) | Data center lease / AI factory campus (PORTS-Pike) | Pike County, Ohio, US (PORTS-Pike / former Portsmouth site) | ~8 GW-IT under 20-year lease; initial 4.25 IT-GW with Nvidia credit support; first ~800 MW targeted 2028 OpenAI Aug 17, 2026: ~8 GW-IT at PORTS-Pike; SB Energy builds/owns/operates under 20-year lease; Nvidia exclusive AI compute, $1.5B SB Energy investment, credit support on initial 4.25 IT-GW (SEC residual-value guarantee capped at $105B cited elsewhere — not campus lease rent). First 800 MW expected 2028. Later Daily/CNBC covered SB Energy S-1 dependency on OpenAI as tenant. | — | Under construction | Link |
| Aug 4, 2026 | CoreWeave | Indonesia facilities (own-and-operate; three sites) | Data center expansion / contracted IT power | Indonesia (Asia-Pacific; first CoreWeave APAC DCs) | 360 MW contracted IT power across three facilities; expected online 2028 Reuters / CoreWeave Aug 4, 2026: three Indonesia facilities totaling 360 MW contracted IT power, own-and-operate, targeted 2028. Capex not disclosed in the Reuters brief. | — | Announced | Link |
| Jul 29, 2026 | Brookfield (developer/operator selected by DOE) | NextEra Energy (dedicated generation); U.S. DOE Paducah Site | AI/HPC campus on former enrichment site + dedicated power | McCracken County, Kentucky, US (Paducah American Energy Hub) | Up to ~1.8 GW utility / >1.2 GW compute stated; $100B investment figure in coalition release Coalition Jul 29, 2026 via Axis: Brookfield+NextEra on DOE Paducah Site. DOE Aug 4 account differs on completion year (2031 vs 2032) and phrasing of capacity. $100B is stated investment, not a signed tenant offtake. PSC approval still required for power service agreement. | $100B | Announced | Link |
| Jul 28, 2026 | Meta Platforms | BlackRock-managed funds (80% venture interest); Meta 20% | Data center JV / lease of entire campus | El Paso, Texas, US | 1 GW compute capacity campus; ~$14B development costs; Meta leases entire campus; online beginning ~2028 Meta/BlackRock Jul 28, 2026: 80/20 venture; ~$14B development costs; 1 GW compute; Meta sole initial occupant via lease. RVG aggregate ~$13B cited in Meta release. | $14B | Under construction | Link |
| Jul 22, 2026 | OpenAI | Georgia Power (power offtake); self-develop campus | Self-build AI data center campus + power contract (Project Camellia) | Effingham County, Georgia, US (Savannah Gateway Industrial Hub) | 3.2 GW contracted power phased 2028–2032; county framed ~$20B minimum investment OpenAI Jul 22, 2026: designing/developing Camellia; 3.2 GW from Georgia Power phased 2028–2032. $20B is the county/incentive framing (Bloomberg cited >$30B at full build — not used as amountUsd). Acres (~1,400) from local coverage of four-building campus. Power figure is contracted utility delivery, not disclosed critical IT load. | $20B | Announced | Link |
| Jul 20, 2026 | Nvidia (reported tenant; Hut 8 named only as investment-grade) | Hut 8 (Beacon Point campus) | Data center lease (15-year phases; campus commercialization) | Nueces County, Texas, US (Beacon Point) | 704 MW IT across two 352 MW leases; 1 GW utility campus; $19.6B base-term contract value Hut 8 Jul 20, 2026: second 15-year $9.8B / 352 MW lease doubles same IG tenant to 704 MW IT; campus base-term $19.6B (renewals could reach ~$50.2B). FT later named Nvidia as tenant; Hut 8 release did not name the counterparty. Related but distinct from Anthropic’s later Lambda cloud offtake on the same campus. | $19.6B | Under construction | Link |
| Jul 14, 2026 | Undisclosed investment-grade global tech tenant | CleanSpark (Sandersville campus) | Data center lease (20-year NNN) | Sandersville, Georgia, US | 175 MW critical IT; ~$6.6B contracted revenue initial term (up to ~$11.6B with extensions); deliveries Q4 2027 CleanSpark Jul 14, 2026: tenant not named. LOI/exclusivity over CleanSpark Texas portfolio (up to 885 MW) noted but not counted as a separate closed lease. | $6.6B | Announced | Link |
| Jul 13, 2026 | Meta Platforms | Blue Owl / Beignet Investors JV; Entergy Louisiana (power) | Hyperscaler AI campus expansion (self-build / JV) | Richland Parish, Louisiana, US (Hyperion) | Expanded to 5 GW compute capacity; >$50B regional investment; ~2 GW targeted by 2030, full ~2032 CNBC on Meta Jul 13, 2026: Hyperion raised from prior ~2 GW / $27B JV framing to 5 GW and >$50B. Meta did not separate critical IT load from site power in the announcement; amount is investment figure, not a bilateral lease rent. | $50B | Under construction | Link |
| Jul 8, 2026 | Meta Platforms | Self-build; Alberta grid partners (Greenlight LP, AltaLink, Capital Power, AESO cited) | AI-optimized data center campus (self-build) | Sturgeon County, Alberta, Canada | 1 GW AI-optimized campus; >CAD $13B investment (USD equivalent not converted here) Meta Jul 8, 2026: groundbreaking on 1GW AI-optimized DC in Sturgeon County, Alberta — first Canada site; >CAD $13B investment. amountUsd null (CAD not converted). IT vs gross capacity not separated. | — | Under construction | Link |
| Jul 6, 2026 | Anthropic | TeraWulf (Raylan Data LLC) | Data center lease (20-year) | Hawesville / Hancock County, Kentucky, US (Justified Data campus) | ~401 MW critical IT load; phased H2 2027 → full early 2028; ~$19B contracted lease revenue TeraWulf Jul 6, 2026 press / 8-K: 20-year lease for ~401 MW critical IT; ~$19B contracted revenue over initial term; IG credit support expected. Separate Abernathy JV sale to Fluidstack-led group is not this row. | $19B | Announced | Link |
| Jun 23, 2026 | Microsoft | Self-build (Village of Mount Pleasant / Racine County) | AI data center campus (Fairwater) — first facility live | Mount Pleasant, Wisconsin, US | First Fairwater facility fully operational; MW undisclosed; second facility targeted 2028; Microsoft cites ~$4.7B statewide WI hyperscale construction spend 2024–2028 (not used as deal amount) Microsoft Jun 23, 2026: first Mount Pleasant Fairwater DC complete/operational after April startup. No IT-load MW in release. Dollar figure in coverage is statewide construction-spend estimate, so amountUsd is null. Acres (315) from campus plan coverage of original site. | — | Live | Link |
| Jun 15, 2026 | Self-build expansion; TVA region power partners | Data center campus expansion | Jackson County, Alabama, US | $1.5B investment across 2026–2027; site MW undisclosed (300 MW cited as contracted regional generation, not campus IT load) Google Jun 15, 2026: $1.5B investment across 2026–2027 to expand Jackson County campus (former Widows Creek coal plant). Critical IT load not disclosed; >300 MW cited as contracted regional generation for TVA area, not campus IT load. | $1.5B | Under construction | Link | |
| May 3, 2026 | Anthropic | SpaceX (xAI Colossus campuses) | Cloud / GPU offtake (Colossus I & II) | Memphis, Tennessee, US (Colossus / Colossus II) | ~$1.25B/month through May 2029 (~$15B/yr); ~325,000 Nvidia GPUs cited in amended S-1 coverage SpaceX S-1 (May 2026) disclosed Cloud Services Agreements with Anthropic for Colossus/Colossus II at $1.25B/month through May 2029; either party may terminate on 90 days’ notice after ramp. GPU count ~325k from amended S-1 coverage; MW not reliably stated as a single leased figure. amountUsd left null (term depends on duration/termination). | — | Live | Link |
| Apr 21, 2026 | Meta Platforms | Self-build | AI-optimized data center campus (self-build) | Tulsa, Oklahoma, US | AI-optimized campus; >$1B regional investment; MW not stated in release Meta Apr 21, 2026 (page also shows Apr 20): first Oklahoma AI-optimized DC; >$1B regional investment. Campus MW not disclosed. | $1B | Under construction | Link |
| Apr 20, 2026 | Anthropic | Amazon Web Services (Trainium / Graviton) | Cloud compute offtake / capacity envelope | AWS regions (incl. Project Rainier / Indiana cited in secondary coverage; sites not fully enumerated in Anthropic release) | Up to 5 GW new capacity; >$100B AWS tech spend over 10 years; ~1 GW Trainium2+3 targeted by end-2026 Anthropic Apr 20, 2026 primary: up to 5 GW and >$100B over ten years on AWS technologies (Trainium2–4, Graviton). Not a named single-site lease; Amazon equity ($5B + up to $20B more) is separate from the offtake spend figure used in amountUsd. | $100B | Announced | Link |
| Apr 9, 2026 | Meta Platforms | CoreWeave | AI cloud capacity offtake (multi-year) | Multiple CoreWeave locations (undisclosed) | ~$21B expanded agreement through Dec 2032; Vera Rubin deployments; prior relationship brings combined ~$35B cited in coverage CoreWeave Apr 9, 2026: expanded long-term Meta agreement ~$21B through Dec 2032 for dedicated AI cloud capacity across multiple sites, including early Vera Rubin. MW/GPU counts not in the company release. | $21B | Announced | Link |
| Mar 18, 2026 | Amazon Web Services | Nvidia | GPU capacity expansion / reservation | AWS regions (global) | >1 million Nvidia GPUs starting 2026 (Blackwell/Rubin architectures cited) AWS blog at Nvidia GTC 2026: deploy more than 1M Nvidia GPUs across AWS regions starting 2026. announced date set to mid-March GTC window (exact keynote day not pinned in the blog slug). Aug 2026 +2M expansion tracked separately as aws-nvidia-gpus-2027-2028. | — | Announced | Link |
| Feb 11, 2026 | Meta Platforms | Self-build | AI / hyperscale data center campus (self-build) | Lebanon, Indiana, US (Boone County) | Designed for 1 GW capacity; >$10B investment cited Meta Feb 11, 2026: groundbreaking on 1GW Lebanon, Indiana campus; investment over $10B. IT vs gross capacity not separated. | $10B | Under construction | Link |